|
|
|
|
|
|
|
Check out our web directory of the UK
roofing and cladding industry
www.roofinfo.co.uk |
Sign up for our monthly news letter. |
|
|
In the first part of the article we
looked at the need for training and planning. This section will deal
with some of the more practical issues.
Co-ordination of trades
Whilst the roof is the domain of the roofer, there are many tradesmen
who need access to the roof to complete their work, and it is often
these people who can affect the finished roof. Scaffolders gaining
access to high level areas will not only install a scaffold onto a
finished low level roof, but can damage the roof by dropping fittings
and poles and walking all over the roof.
Lightning conductor contractors will install
strike plates and aerial rods through the roof covering after it is
finished and will often not come onsite while the roof is being
installed as this would require additional visits to site.
Electricians installing ventilation slates, or tiles,
long after the roof has been finished. Plumbers installing vent pipes
and boiler flues through the roof and carpenters installing roof windows
and dormers with no consideration for the slate or tile module, making
it difficult to finish at the side and top edge abutments. If all trades
talked to each other prior to work starting, they could help each other
by appreciating each other’s problems, and coming to an amicable
solution. This normally only happens when the tradesmen are on site and
face to face. But as the roof is one of the first elements to be
completed the roofer is often long gone before the electrician or
plumber arrives on site so it is the manager’s role to think ahead.
It is also quite common for the order of construction
to change such that because of ground work problems the first phase of
the building is delayed and can not be roofed first and therefore the
roofing work starts in another place and work is done out of sequence,
resulting in some elements being done back to front. How often have you
seen the left hand half of an interlocking tiled roof finished and the
right hand side left pending other works or a roof being tiled or slated
before the fascia boards have been installed.
Instructions
Most proprietary products come with fixing instructions, but there are
many products like slate that do not come with instructions, and rely
upon the skill of the tradesmen to install them correctly. Where
instructions are provided they should be read, understood and followed,
as often compliance with the fixing instructions will ensure the product
performs its function correctly and will be covered by a guarantee. Too
often fixing instructions are not read or understood and therefore not
installed correctly resulting in failure. Of course, fixing instructions
tend to cover the majority of situations and discussion with the
manufacturer is needed if used outside of the situation normally used.
The fixing instructions should be seen by the specifier
and the managers, but as they only come with the products that arrive on
site, this does not often happen. It is essential that fixing
instructions are seen and understood at all stages of the planning
process as often they will have an effect on the overall plan. It may be
that an electric screwdriver is needed which will need a power supply,
or a bench mounted disc cutter, which would be quicker to use if located
on the scaffolding, is recommended. Too often technical literature from
manufacturers does not contain sufficient information for the managers
who need to plan the work. |
|
Over planning
The plan should never rule the project. With fast track projects where
there is a deadline and a high penalty for overruns, it is essential
that everybody understands their part and meets the plan targets, but
removing scaffolding before roofing works have been completed, just
because the plan says that at 12.30 on a particular day the scaffold
will come down, is a breach of health and safety. Plans need to allow
for inclement weather, unforeseen circumstances like theft of materials,
material delivery bottle-necks from tower cranes, road closures due to
civic events, or lack of accommodation due to big sporting events. If
the programme is tight it is likely to fail. But, having said that, you
cannot plan for every eventuality and, therefore, records need to be
kept of all delays, and day to day progress honestly appraised and set
against the plan, to account for any delays and to add to the learning
process.
Conclusion
Undertaking any project requires planning that starts years before the
project starts on site, with the training of staff. When a project is
put out to tender there should be full and adequate documentation to
allow the next level down the contractual chain to be able to both
provide a competitive quote, and to plan the project accurately. Too
often projects are not planned adequately and bumble along hand to
mouth, and these are the ones that appear to go wrong and end in
disputes and litigation, cut into profit margins and do none of us any
good. We are not suggesting undertaking a full critical path analysis of
each and every element of each tradesman’s work, timing the installation
of each nail down to seconds. We are talking about a respectable plan
that can be presented and compared with other trades to highlight
difficulties and allow the difficulties to be resolved prior to work
starting on site. Once work has started on site, expect problems to
arise. If 95% of all problems can be resolved before arriving on site,
only 5% will need to be resolved on site, not the other way around.
Tips
- If roofing is the only work element,
such as re-roofing a house, then coordination with the client is
essential.
- Speak with the other contractors on
the project; they should not be seen as competitors but colleagues.
They will have plans and need to blend theirs with yours. If you do
not have a plan then that is made more difficult.
- Always review the project when it is
complete and see where things could have been done better for next
time.
|
Compiled
by Chris Thomas, The Tiled Roofing Consultancy, 2 Ridlands Grove,
Limpsfield Chart, Oxted, Surrey, RH8 0ST, tel 01883 724774 |
|